Phase | Deliverable | Deliverable Language |
Approval Period (upon receipt of deliverable) |
---|---|---|---|
Phase 1: Assessment
|
Inception Report | English | 2 weeks |
Project Plan | English | 2 weeks | |
Quality Assurance Plan | English | 1 weeks | |
Risk Analysis Document | English | 1 week | |
Determination of Administrative Burdens and SCM Electronic Storage | English & Arabic | 3 week | |
Process Maps and Process tables Electronic Storage | English & Arabic | 2 week | |
Strategy Paper | English & Arabic | 2 week | |
Assessment Report | English & Arabic | 3 week | |
Workshop(s) to discuss the finding of the assessment phase | Arabic | 1 week | |
End-of-phase report | English | 2 weeks | |
Phase 2: Analysis and Diagnosis | Analysis and Diagnosis Report | English & Arabic | 3 weeks |
Workshop(s) to discuss the finding of the Analysis and Diagnosis phase | Arabic | 1 week | |
End-of-phase report | English | 2 week | |
Phase 3: Design |
Legal Database Functional Design | English | 2 weeks |
Design Report | English and Arabic | 3 weeks | |
Standardized Input Forms and Output Documentation | Arabic | 2 weeks | |
Filled out Business Requirement Document | English and Arabic | 2 weeks | |
Workshop(s) to discuss the finding of the design phase | Arabic | 1 weeks | |
End-of-phase report | English | 2 weeks | |
Phase 4: Implementation
|
Operations manual | Arabic | 1 week |
Training plan | English | 1 week | |
Training materials | Arabic | 2 weeks | |
Selected employees coaching and training | Arabic | 2 weeks | |
Frontline staff training | Arabic | 2 weeks | |
Knowledge transfer plan and implementation | Arabic | 2 weeks | |
Train the trainers | Arabic | 2 weeks | |
Study tours | English | 2 week | |
Study tours evaluation report | English | 2 week | |
Statement of service standards | Arabic | 1 week | |
Capacity building reference material | Arabic | 2 weeks | |
“One-Stop” Shops incorporation in the implementation | English & Arabic | 2 weeks | |
Structured inspections | Arabic | 1 week | |
Workshop(s) to discuss the finding of the implementation phase | Arabic | week | |
End-of-phase report | English | 2 week | |
Phase 5: Finalization and Closure | Verification of Deliverables | English & Arabic | 2 weeks |
End of Project Report | English & Arabic | 2 weeks |